High School Library Media Center Renovation
The Amity High School Library Media Center is being transformed into a modern learning environment designed to better support today's students and tomorrow's opportunities. The renovation will create a more welcoming, flexible, and technology-rich space where students can read, research, collaborate, create, and learn throughout the school day.
The redesigned Library Media Center will feature a variety of learning spaces to meet different student needs, including quiet reading areas, collaborative workspaces, a dedicated library classroom, podcast and recording rooms, and flexible furniture that can be easily reconfigured for classes, independent study, or special events. The project also improves accessibility, student traffic flow, visibility throughout the space, lighting, acoustics, and access to technology and power.
This page will provide regular updates throughout construction, including project milestones, photographs, and information about how library services will continue while work is underway.
For more information about the project, please contact Steve Martoni, Director of Facilities.











WHAT YOU'LL SEE WHEN IT'S FINISHED
- Flexible spaces for both collaboration and independent study
- A dedicated Library Media Center classroom Podcast and recording studios for student projects
- A quiet reading room
- New collaborative seating and modern furnishings
- Improved lighting, acoustics, and access to electrical power
- A redesigned entrance and circulation desk that improve student flow and visibility
- Updated technology support spaces and infrastructure throughout the Library Media Center
PROJECT UPDATES
CONSTRUCTION TIMELINE
Project Schedule June 2026 - March 2027
- Planning
- Contract Signing: June 15
- Submittals: 3 Weeks
- Construction
- Worksite Prep & Demolition: July 7
- Demo Complete / Layout: July 22
- Mechanical Systems
- Carpentry & Drywall: September 22
- Finishes
- Acoustical: October 27
- Glazing: November 10
- Flooring: November 28
- Casework: December 1
- Painting: December 15
- Closeout
- Substantial Completion: December 29
- Punch List: January 5
- Final Completion: March 25, 2027